Friday, June 5, 2026
Village Voice News
ADVERTISEMENT
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
Village Voice News
No Result
View All Result
Home Letters

Procurement Commission adopted defective report and rubber stamped award

Admin by Admin
January 8, 2024
in Letters
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

Dear Editor,

The Public Procurement Commission (PPC) has finally issued a report based on a complaint from a contractor. Predictably, the report is a whitewash of the administrative review process and falls short of the standards expected from a constitutional agency.

READ ALSO

Understanding Concussions

Ramsammy’s Flood Spin Drowns in Reality

By way of background – the Office of the Prime Minister issued an invitation to bid for line hardware in March 2023 with the bid opening slated for April 2023. Five bids were returned, and unsurprisingly the lowest bid by Akamai Inc. was the only bid deemed non-responsive. Akamai Inc. by the way is the sole distributor of the requested line hardware; hence it was expected that the company would submit the lowest bid.

The evaluation committee deemed Akamai Inc. non-responsive because it was claimed that:

  1. a) the bidder failed to submit documentary evidence to demonstrate supply of similar goods in at least 1 contract in the last two (2) years to a minimum value of G$5M and
  2. b) the bidder failed to provide a letter stating that the company had no terminated projects.

This is where it becomes interesting. There was no prescribed format for the submission of evidence of previous projects, and hence Akamai Inc. submitted a spreadsheet detailing all their previous contracts, detailing the procurement agencies as well the contract sums (see attached). However, not surprisingly, in an effort to deem the bidder non-responsive, the procurement agency found this detailed listing unacceptable.

Additionally, a simple conversation with the bidder revealed that he did in fact fulfill the second requirement which the evaluation committee deemed non-responsive – which was a letter addressed to the procuring entity stating specifically that none of their projects was ever terminated (see attached) – clear evidence that this information was fraudulently omitted by the evaluation committee or ignored.

In arriving at its report to support the award, the PPC never contacted the bidder, seeking clarifications on the claims for debarment made in the evaluation report, as is standard when reviewing complaints, whereby all parties to the complaint should be given an opportunity to defend their position. The PPC simply adopted a defective report, performed no investigative analysis and rubberstamped the award.

When contacted, the AFC nominated commissioner within the PPC highlighted that a) both opposition commissioners found the submission of the list of projects comprehensive and acceptable and b) that they were unaware that the bidder had actually submitted the claimed missing letter regarding terminated projects. The AFC nominated commissioner also informed that she recommended that natural justice procedures be adopted, whereby all parties should be given an opportunity to respond before a final decision is made by the commission, however this was overruled by the majority vote of the Commission.

Strangely, but not unsurprisingly, the PPC failed to highlight that section 5 (5) (a) of the Procurement Act specifically states “a procuring entity may not disqualify a supplier or contractor on the ground that information submitted concerning the qualifications of the supplier or contractors was inaccurate or incomplete in a non-material respect.” The claimed incomplete information as supplied by this contractor are all non-material in every respect, and in accordance with the Act, such non material deficiencies can be remedied.

The PPC, a constitutional agency with an annual budget of almost $300M has taken eight months to respond to the bidder’s complaint, and in the end simply rubber stamped a defective and possibly fraudulent evaluation report, without even giving the complainant the opportunity to prove otherwise.

The public would have been mistaken if they assumed that any investigation by PPC, would have been in-depth, whereby a review of the entire bidding process would have been conducted, including a full review of all documents submitted by all bidders, review of the responsiveness of the bidders and then a final determination of who is deemed successful.

I anticipate a similar rubber stamping of NPTAB’s award of the Belle Vue pump station, when or if, the PPC ever responds to a complaint lodged since October 2023. I also expect a similar undemocratic rubber stamping to the complaint on the award of the Bamia Secondary school lodged since February 2023 as democratic structures and institutions in our nation continue to falter and become unrecognizable.

Yours truly,

David Patterson

Procurement Act

PPC Response – Akamai

Previous Projects

ShareTweetSendShareSend

Related Posts

Letters

Understanding Concussions

by Admin
June 4, 2026

Dear Editor, Concussions are often misunderstood injuries that can have severe implications for those affected. Despite being termed "mild," these...

Read moreDetails
Letters

Ramsammy’s Flood Spin Drowns in Reality

by Admin
June 4, 2026

Ramsammy’s Flood Defense Collapses Under the Weight of Reality Dr. Leslie Ramsammy’s column in Guyana Times is not an analysis—it...

Read moreDetails
Letters

How did he die? Who was he fronting for?

by Admin
June 4, 2026

Dear Editor, As my Christian priest explained in the sermon no matter how much wealth you acquired from legitimate and...

Read moreDetails
Next Post

Letter re Guyana at the United Nations


EDITOR'S PICK

Widespread Rental of Young Professional Homes Raises Concerns About Fairness in Distribution Process

January 31, 2024
Former President David Granger

Former President Granger revisits 2020 Elections shenanigans, the ‘Holladar effect’

August 25, 2024
Lebron James started hi NBA career with Cleveland in 2003

NBA: LeBron James leads the LA Lakers to victory against former side Cleveland

March 22, 2022
Dr. Mark Devonish

Exposing PPP propaganda

August 13, 2023

© 2024 Village Voice

No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us

© 2024 Village Voice