Thursday, August 20, 2026
Village Voice News
ADVERTISEMENT
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
Village Voice News
No Result
View All Result
Home News

Duncan Flags Delays, Transparency Gaps in Mabaruma Road Projects

Admin by Admin
January 15, 2026
in News
APNU MP Sherod Duncan

APNU MP Sherod Duncan

0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

A Partnership for National l Unity (APNU) Member of Parliament Sherod Duncan has raised concerns over delays, poor execution and a lack of transparency surrounding two major road projects in Mabaruma, Region One, following a four-day visit to the area earlier this month.

In a statement issued on Tuesday Duncan said he visited Mabaruma from January 9 to 12, accompanied by MP Juretha Fernandes and other team members, to assess infrastructure projects after repeated complaints from residents.

READ ALSO

Court Halts Maha Sabha Ashram Works as Management Dispute Deepens

Mohameds Demand Anderson Recuse Himself, Urgent Disclosure of Records

He identified the G$80.6 million Barabina Hill Road Project and the G$200 million Silver Hill (Hobo Hill) Road Project as emblematic of what he described as a pattern of “announcements without delivery, weak accountability, and poor execution.”

On the Barabina Hill Road, Duncan said he had visited the area in both 2024 and 2025 and repeatedly heard complaints about the road’s deteriorating condition.

Barabina Hill Road (Sherod Duncan’s photo)

He noted that after those concerns were raised publicly, the government announced around July—on the eve of elections—that work would begin “within two weeks.” However, he said the project has since stalled, with only limited activity by one contractor starting just days ago.

“This stop-start approach reflects a familiar problem: communities endure prolonged hardship while projects are announced, paused, and intermittently revived without clear timelines or sustained on-the-ground delivery,” Duncan said.

He added that although the G$80.6 million allocation was publicly indicated and the project advertised under the Ministry of Public Works in 2025, there is no clear disclosure identifying the awarded contractor, award date or final contract sum in the records of the National Procurement and Tender Administration Board.

Duncan also raised concerns about the Silver Hill (Hobo Hill) Road Project, saying residents reported that sections of the newly constructed road had to be dug up due to improper construction.

Silver Hill Road (Sherod Duncan’s photo)

According to Duncan, residents claim the road’s thickness does not meet specifications and that the surface remains rough and unsafe. He said requests for the bill of quantities were reportedly refused.

The Silver Hill project, Duncan noted, was awarded in 2024 under the hinterland roads programme, with a contract valued at approximately G$200 million to construct about 1.2 kilometres of rigid concrete pavement linking Hobo Hill to the Mabaruma airstrip corridor.

While funding and tendering are traceable, he said progress updates have largely come through budget speeches and ministerial visits rather than regular public disclosures.

“These two projects illustrate a broader issue: infrastructure announcements are being treated as outcomes, while transparency, quality assurance, and completion remain unresolved,” Duncan said.

He said residents of Mabaruma deserve roads built to standard, clear information on contracts and costs, and consistent delivery, adding that he will continue to press for “full disclosure, accountability, and remedial action” to ensure public funds result in durable infrastructure in Region One.

ShareTweetSendShareSend

Related Posts

Maha Sabha
News

Court Halts Maha Sabha Ashram Works as Management Dispute Deepens

by Admin
August 19, 2026

The legal battle over control of the Guyana Sanatan Dharma Maha Sabha has intensified, with the High Court imposing significant...

Read moreDetails
News

Mohameds Demand Anderson Recuse Himself, Urgent Disclosure of Records

by Admin
August 19, 2026

Attorneys for Nazar and Azruddin Mohamed have escalated their challenge to the Caribbean Court of Justice (CCJ), demanding urgent disclosure...

Read moreDetails
News

President Ali Attacks, Opposition Leader Mohamed Demands Evidence

by Admin
August 19, 2026

President Irfaan Ali and Opposition Leader Azruddin Mohamed have become locked in a fierce public confrontation over corruption, credibility and...

Read moreDetails
Next Post
Stabroek Market

Stabroek Market Reflects Neglect


EDITOR'S PICK

Magnitude 7.2 quake rocks Haiti, dozens killed 

August 15, 2021
Dr Wayne Wesley, Registrar and CEO of CXC® addressing the audience, beside Master of Ceremonies. Ms Jodine Williams, Senior Manager - Syllabus & Curriculum Development Unit, CXC

CXC launches strategic five-year plan

February 3, 2021
United Nations Annalena Baerbock, President of the UN General Assembly, addresses a session on Who Brokers Trust Now? at the World Economic Forum in Davos, Switzerland.

UN Assembly president defends multilateralism, UN Charter in Davos

January 22, 2026
Teammates congratulare West Indies' Alzarri Joseph after he dismissed Australia's Usman Khawaja on day two of the first cricket Test match at Kensington Stadium in Bridgetown, Barbados, Thursday, June 26, 2025. (AP Photo/Ricardo Mazalan)

West Indies demand ‘penalty’ on umpires for ‘blatant’ wrong calls in Australia’s favour: ‘Could make or break careers’

June 29, 2025

© 2024 Village Voice

No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us

© 2024 Village Voice