Sunday, September 27, 2026
Village Voice News
[adning id="37476"]
ADVERTISEMENT
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
Village Voice News
No Result
View All Result
Home News

GPL’s 46.5-megawatt power generation plant set for mid-August finish 

Staff Reporter by Staff Reporter
May 25, 2021
in News
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

Prime Minister, Mark Phillips on Monday conducted an on-site inspection of the 46.5-megawatt power generation plant being constructed by Wärtsilä, at the Guyana Power and Light (GPL), Garden of Eden Power Station.

It is expected that the plant will begin its testing phase in early June and will become fully operational a few months after.

READ ALSO

Government Moves to Tackle Toxic Workplaces

MV Barima Families Still Wait as 30+ Remain Missing and Salvage Questions Persist

According to a Department of Public Information (DPI) release, the Prime Minister said that although there was extensive work done since his last visit in October 2020, the Government understands that the project’s original date of completion would not be met.   He pointed out that the main objective is to give Guyanese a quality product and indicated that efficiency will not be sacrificed for expediency.

“We have to work with the contractor to ensure that what is delivered here to the people of Guyana is in keeping with the same high standard, quality and reputation that Wärtsilä has internationally… A lot of work has been done, but the work has been affected negatively by COVID-19 and the weather conditions”.

As a result, the project which was scheduled to be completed by the end of June, will now be finished in August.

The Prime Minister had said that the project was a part of the Government’s plan for reliable electricity and will greatly enhance the consistency of electric power in the Demerara – Berbice Interconnected System.

TESTING 

Minister within the Ministry of Public Works, Deodat Indar, who accompanied the Prime Minister, said that the new power generation facility is the biggest project in terms of single location generating capacity. “There are two parts of the project which will cause the extra delay, which are the transformers and the fuel tank, we have an alternative arrangement for fuel, because we have an existing facility here, but the plant itself will be testing during June and July… we want to make sure that when the project comes fully on stream there will be no issues, because it’s the biggest project in terms of single location generating capacity”.

Also present was Chief Executive Officer of GPL, Bharat Dindyal.

ShareTweetSendShareSend

Related Posts

News

Government Moves to Tackle Toxic Workplaces

by Admin
September 26, 2026

Intimidation, disrespect and toxic workplace relationships have become sufficiently entrenched in some Guyanese workplaces that the Government is now calling...

Read moreDetails
MV Barima protest sign demanding accountability
News

MV Barima Families Still Wait as 30+ Remain Missing and Salvage Questions Persist

by Admin
September 26, 2026

Seventy-three lives have been lost, 76 people survived and at least 30 remain unaccounted for, but more than two months...

Read moreDetails
Attendees at President Irfaan Ali speaking at September 24, 2026 at Jericho Palace Banquet Hall in Queens Village
News

Ali’s “Thousands” in Queens Raise Questions as WIN Protesters Demand Answers

by Admin
September 26, 2026

President Irfaan Ali used a diaspora meeting in Queens to paint a picture of an economy racing ahead, claiming Guyana...

Read moreDetails
Next Post
Jagdesh Jaddunauth showing part of his garden that is under water

Floodwaters ruin livestock, cash crops in Black Bush Polder 


EDITOR'S PICK

Christians should never be coerced into sowing seeds

March 26, 2023
Minister of Housing and Water, Hon. Collin Croal

Over $3.9M in contracts handed over for installation of distribution system & storage facility for Kwebanna water supply system

January 24, 2023

GTUC Condemns Aurora Goldfield Worker Abuse, Demands Immediate Action

November 30, 2025

WORD OF THE DAY: EVINCE

July 27, 2023

© 2024 Village Voice

No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us

© 2024 Village Voice