Thursday, June 4, 2026
Village Voice News
ADVERTISEMENT
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
Village Voice News
No Result
View All Result
Home News

Wismar/Mackenzie bridge now 95.4 per cent complete

Admin by Admin
May 13, 2026
in News
Aerial view of the progress on the construction of the NMWB

Aerial view of the progress on the construction of the NMWB

0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

With the Wismar/Mackenzie Bridge on track to become fully operational by June, construction is progressing steadily, with works now 95.4 per cent complete.

According to an update from the Ministry of Public Works on Tuesday, 95 per cent of the concrete has been placed on the 220-metre-long precast structure.

READ ALSO

Women Gain Influence in Private Sector Commission Leadership

Energy Crisis Highlights Dangerous Reliance on Foreign Suppliers- Dr. Adams

Additionally, 60 per cent of the box culverts on both sides of the bridge have been completed.

These reinforced rectangular concrete structures are designed to provide durable, high-capacity channels for drainage, water management and utility passage beneath infrastructure.

The state-of-the-art structure, being constructed by China Railway Construction (Caribbean) Co Ltd, is expected to significantly improve connectivity in Linden by facilitating smoother traffic flow between the Mackenzie and Wismar communities.

To complement the bridge, two access roads and roundabouts are being developed, while the connecting roadways will be expanded into four lanes.

The upgraded road network will feature a geo-carriageway, median and traffic islands aimed at enhancing road safety and easing traffic congestion.

Roundabouts are also being installed on both sides of the bridge to connect it seamlessly to the Linden–Mabura Road and the wider highway network.

The project forms part of the broader upgrades planned for the region, including upgrades along the Linden/Soesdyke Highway.

Meanwhile, the ministry reported that there were zero incidents or accidents recorded at the eastern laydown yard, trestle bridge and west bank construction sites.

Relocation works by the Guyana Water Incorporated (GWI) on both the eastern and western banks have also been completed.

Upon completion, the bridge is expected to deliver long-term economic, social and environmental benefits by easing travel for residents and improving the movement of people and goods in and out of Linden.

At the same time, other major bridge initiatives are advancing across Guyana.

These include the proposed Kurupukari Bridge across the Essequibo River, which is expected to replace the current pontoon crossing.

Sections of the old Demerara Harbour Bridge are also being repurposed to create additional transportation links, including the Timehri Sandhills-to-Bartica corridor, where geotechnical studies have already been completed.

Similar infrastructure works are expected to support connectivity between Leguan and Wakenaam, while an active task force continues to finalise designs and advance the projects.

Plans for a new Berbice River Bridge are also progressing, with negotiations and financing discussions currently ongoing.

DPI

ShareTweetSendShareSend

Related Posts

L-R Kathy Smith- Vice Chairwoman PSC, Josephine Tapp- President WCCIG                                                                                        
News

Women Gain Influence in Private Sector Commission Leadership

by Admin
June 4, 2026

Women have secured greater influence within Guyana's leading private sector body following the re-election of the Private Sector Commission's (PSC)...

Read moreDetails
Former Head of the Environmental Protection Agency (EPA), Dr. Vincent Adams
News

Energy Crisis Highlights Dangerous Reliance on Foreign Suppliers- Dr. Adams

by Admin
June 4, 2026

Energy expert Dr. Vincent Adams has sharply criticised the Government of Guyana's handling of the country's electricity sector, arguing that...

Read moreDetails
Natasha Singh, MP (WIN)
News

Singh Rejects Norton’s Extradition Claim Against Mohamed, Says Remarks Undermine Opposition Unity

by Admin
June 4, 2026

A new disagreement has surfaced within the opposition after We Invest in Nationhood (WIN) Member of Parliament Natasha Singh rejected...

Read moreDetails
Next Post

Press Release: Contract signed for dredging of Demerara River


EDITOR'S PICK

Poverty is rampant in oil rich Guyana

October 19, 2024
Lindsayca/CH4 (Google photo)

Guyana Moves to Arbitration in Dispute with Lindsayca/CH4 Over EPC Contract

March 11, 2025

WANSat Brings Fast and Affordable Satellite Broadband Internet Service to Guyana

February 28, 2023

Jonas, Forde Clash in Court Over Authority to Lease Critchlow Labour College Property

May 12, 2026

© 2024 Village Voice

No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us

© 2024 Village Voice