Thursday, September 10, 2026
Village Voice News
[adning id="37476"]
ADVERTISEMENT
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
Village Voice News
No Result
View All Result
Home News

GPL in 9.6MW boost for holidays

Staff Reporter by Staff Reporter
December 6, 2020
in News
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

Guyana Power and light Inc. (GPL) has announced the arrival of six  1.6 Megawatt (MW) Caterpillar Units to help boost power supply for the Christmas season.

READ ALSO

Guyana Expands Regional Influence With New Amazon Health Leadership

CARICOM Steps Up Haiti Diplomacy as December Elections Approach

In a press release GPL said three of the units will be installed at GPL’s Sophia, Georgetown location, while the other three will be placed at GPL’s Onverwagt (West Berbice) office.

An additional four units, with total capacity of 6.4MW, have been placed on standby by the supplier in case there is a failure of any of the six units purchased by GPL, the release said.

The company said the arrival of the units is in keeping with its  commitment to boost generation capacity and provide customers in the Demerara-Berbice Interconnected System with reliable electricity.

The six power modules and associated transformers were procured at a cost of $475,422,029 and $80,886,430 respectively, the release added.

Meanwhile, Minister within the Ministry of Public Works, Deodat Indar during an interview with the Department of Public Information said that when the PPP/C Government took office they recognised weaknesses in the company’s operations and instituted two main measures.

“One was the Giftland Power Producing Agreement, which was for five megawatts and that five megawatts is already incorporated in GPL grid, and the other was the purchase of 10 megawatts of power generating sets from MACORP,” Minister Indar said.

He added, “we bought six sets and each one of them is 1.6 megawatts but in the arrangements when we bought the sets, we got four additional sets as backup and each one of these sets carry generating capacity of 1.6 megawatts.”

Minister Indar further stated that the sets have already been dispatched to their locations. The Sophia, Canefield and Onverwagt sub-stations will each receive three gensets and the remainder will go to the Anna Regina sub-station.

The delivery of the sets is timely as the Minister said chief among the purpose at this time is to provide extra power during the Christmas holiday.

“The demand will go about 124.5 megawatts so we wanted to make sure that we have the baseline capacity to generate the power.”

Minister Indar noted that since the new gensets use light fuels these would be more costly than the company’s Wartsila sets which use heavier fuel. However, a management plan is in place.

“These are smaller sets so they will work with light fuel oil, so we have to manage the load on a daily basis to know when we will put them in. […] GPL has that plan where they will kick in the generator on or off based on how they see the demand across the country,” the Minister said.

Additionally, the Minister relayed that GPL has been successful in securing an overseas contractor to repair the severed submarine cable from Vreed-en-Hoop to Kingston.

The team is expected to be in Guyana by next week to begin works and reintegrate the 7 megawatts back into the system.

ShareTweetSendShareSend

Related Posts

Minister of Health Dr. Frank Anthony
News

Guyana Expands Regional Influence With New Amazon Health Leadership

by Admin
September 10, 2026

Guyana is taking on a new regional leadership role in health, assuming the Pro Tempore Presidency of the Special Commission...

Read moreDetails
From L-R: Haiti's Minister of Foreign Affairs, Her Excellency Raina Forbin; EPG Members, former Prime Ministers Mr. Perry Christie of The Bahamas; Dr. Kenny Anthony of Saint Lucia; and Mr. Bruce Golding of Jamaica
News

CARICOM Steps Up Haiti Diplomacy as December Elections Approach

by Admin
September 10, 2026

The Caribbean Community is intensifying its diplomatic efforts in Haiti as the country struggles to overcome a prolonged political crisis...

Read moreDetails
Warapoka Generator (MP Sherod Duncan's photo)
News

Four Years Later, Warapoka Generator Remains Idle as Residents Await Electricity

by Admin
September 10, 2026

 More than four years after residents of Warapoka, Region One, were promised a generator-based electricity supply, the community remains without...

Read moreDetails
Next Post

FAO helping Guyana boost Seabob production


EDITOR'S PICK

Former Minister of Public Infrastructure and MP David Patterson

MP David Patterson dispels PM Mark Phillips “untruths”

April 5, 2024
The Grand Ethiopian Renaissance Dam has been a subject of an ongoing dispute between Egypt, Ethiopia, and Sudan [File: Adwa Pictures/AFP]

Ethiopia slams ‘belligerent threats’ after Trump dam comments

October 25, 2020
Former President David Granger

PPP’s marginalisation policies undermining future of young people-Granger

February 9, 2025
Dr. Henry Jeffrey

‘Autocracy: A Tyranny of Gaslighting’

April 26, 2026

© 2024 Village Voice

No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us

© 2024 Village Voice