Monday, October 26, 2026
Village Voice News
ADVERTISEMENT
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
Village Voice News
No Result
View All Result
Home Editorial

Nine Weeks to First Power: New Money Demands Raise Questions Over Guyana’s Wales Energy Deadline

Government agreed to US$97M contract increase in May, but fresh reports of funding demands and possible delays raise questions about the December deadline and who will bear the additional costs.

Staff Writer by Staff Writer
October 26, 2026
in Editorial
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

GEORGETOWN, GUYANA, October 26, 2026 — With approximately nine weeks remaining before the Wales Gas-to-Energy project is supposed to deliver its first electricity to Guyana’s national grid, fresh reports of financial difficulties, additional payment demands and a possible failure to meet the December deadline have placed renewed scrutiny on one of the country’s largest infrastructure investments.

The latest concerns follow a May 14, 2026 settlement in which the Government of Guyana agreed to increase the contract price for the power plant and Natural Gas Liquids facility by approximately US$97.15 million. In return, contractor Lindsayca Guyana Inc. committed to a revised delivery schedule, with penalties potentially reinstated if agreed milestones were missed.

READ ALSO

Who Really Controls Guyana’s Future?

The State Must Answer for Kitty Shooting

The original US$759 million contract consequently increased to US$856.15 million, a rise of 12.8 percent. The settlement resolved two disputes concerning soil stabilisation and delays at the Wales construction site. Both parties also agreed to forgo their respective rights to historical liquidated damages, subject to a contractual cap of 10 percent.

According to the Office of the Prime Minister’s May 14 statement, the revised agreement established three milestones: first electricity by the end of December 2026, commissioning of all four gas turbines by the first quarter of 2027, and completion of combined-cycle operations by June 2027.

The government explicitly stated that failure to meet these milestones would permit it to reinstate liquidated damages against the contractor.

Fresh claims raise questions

Those commitments are now being tested.

On October 18, Kaieteur News reported, citing unnamed sources, that the United States Embassy in Georgetown was supporting a request by Lindsayca for an additional US$102 million to complete the project.

A second report, published October 25, claimed that Lindsayca had informed the government it would be unable to deliver electricity to the national grid by Christmas. The newspaper also reported a further funding request ranging from US$120 million to US$170 million.

These are serious allegations, but they have not been independently confirmed. The reports rely on unnamed sources, and no publicly verified agreement approving the additional funding has been identified. Neither has an official announcement been located confirming that the December deadline has been abandoned.

The reported figures should also not be treated as separate amounts to be added together. It remains unclear whether they represent successive negotiations, revised estimates or different components of the same funding request.

What is confirmed is that Lindsayca has sought additional resources since the May settlement.

During a September press conference, President Irfaan Ali acknowledged that the contractor had requested more money, but said the government had not discussed approving a further payment.

A dispute dating back to 2024

The current financial uncertainty follows a history of disagreements over the cost and timetable of the project.

In April 2024, Reuters reported that contractors involved in the project were seeking US$90 million in additional payments related to cost overruns. Vice President Bharrat Jagdeo subsequently challenged that figure, telling Stabroek News that the dispute involved US$50 million rather than US$90 million.

Jagdeo said Engineers India Limited, the firm supervising construction, had examined the contractor’s financial claim and rejected it as lacking merit. The disagreement proceeded through the contractual dispute-resolution process.

The May 2026 settlement increased the contract by approximately US$97 million, although publicly available information does not establish that the settlement amount corresponds directly to the claim disputed in 2024.

Meanwhile, Kaieteur News reported in April 2026 that the contractor was seeking as much as US$250 million in additional funding to complete the works.

The repeated appearance of substantial financial claims raises an important question: how much of the project’s rising cost is attributable to legitimate changes in construction requirements, and how much should remain the contractor’s responsibility under its existing agreement?

Difficult ground, expensive consequences

There is documented evidence that construction conditions at Wales have been difficult.

During a September site inspection, Lindsayca’s country manager, Luis Pirela, explained that extensive soil modification had taken approximately 18 months before foundation work could proceed. According to the government’s account, approximately 10,000 piles were installed, some extending 38 metres into the ground.

US Ambassador Nicole Theriot subsequently defended the contractor, telling Kaieteur News that the marshy site had required more than US$100 million in remediation work and expressing confidence that Lindsayca would meet its year-end commitment.

These explanations provide important context for the delays. They do not, however, resolve the separate contractual question of which party is legally responsible for the additional costs.

The May settlement was intended to address earlier disagreements and establish a revised delivery timetable. Any new request for funding therefore requires a clear explanation of what has changed since that agreement.

What happens to the penalties?

The financial consequences of another delay could be substantial.

In September 2024, government officials disclosed that the original contract provided for liquidated damages of approximately US$377,000 per day, equivalent to about US$11.3 million per month, subject to the applicable contractual provisions.

The May 2026 agreement waived historical claims but expressly preserved the government’s ability to reinstate liquidated damages if the new milestones were missed.

Whether the earlier daily rate remains applicable under the revised arrangements cannot be confirmed without examining the settlement agreement and amended contract.

The government has not publicly detailed how any reinstated penalties would be calculated, whether further extensions are being considered, or whether a new financial agreement would alter those provisions.

The distinction matters. A settlement that increases the contract price in exchange for firm delivery commitments provides protection for taxpayers only if those commitments can be enforced.

First power is not full power

Even if the contractor meets the December deadline, Guyanese consumers should understand what is actually being promised.

According to the government’s September progress reports, the immediate target is approximately 57 megawatts from the first gas turbine. The four gas turbines are intended to provide a combined 228 megawatts, while the addition of steam turbines will eventually raise the facility’s generating capacity to 300 megawatts.

The May agreement sets June 2027 as the deadline for combined-cycle operation, approximately six months after first power.

Prime Minister Mark Phillips has also clarified that the government’s promised 50 percent reduction in electricity tariffs is expected after the power plant becomes fully operational, rather than immediately upon commissioning of the first turbine.

For businesses currently operating with expensive electricity, that distinction is significant. The promised savings cannot reasonably be incorporated into near-term operating budgets until the generating capacity is delivered and the revised tariffs are formally implemented.

Could Guyana face another costly interim arrangement?

The October 25 Kaieteur News report also alleged that the government was preparing to acquire a third rented power ship from Turkish supplier Karpowership, possibly arriving in December.

Guyana already relies on two rented power ships with capacities of approximately 36 and 60 megawatts to supplement domestic generation.

The reported third vessel has not been independently confirmed, but its possible procurement raises additional financial questions.

If Guyana must continue renting generating capacity while waiting for the Wales facility, the cost of delay extends beyond the construction contract. It includes power-ship rental arrangements, imported fuel, financing and other operating expenses needed to maintain electricity supplies.

In May, the government maintained that the facilities and related publicly funded infrastructure would remain within a US$1.1 billion expenditure ceiling, including contingencies. That figure covers specified government-funded components and should not be confused with the cost of the separate offshore gas pipeline developed by ExxonMobil.

Any newly approved payments would therefore need to be reconciled with the government’s published budget.

Nine weeks remain

The immediate issue is no longer whether Guyana needs the Gas-to-Energy project. Its potential benefits, including additional generating capacity and lower electricity costs, have been central to the government’s energy strategy for years.

The question is whether the country will receive the infrastructure on the revised terms negotiated in May.

Several important matters remain unresolved: Has Lindsayca formally notified the government that the December deadline cannot be met? Has a new funding request been evaluated by Engineers India Limited? Is another contract amendment being considered? What amount has actually been disbursed under the May settlement? And will liquidated damages be pursued if the contractor fails to deliver?

These questions can be answered through publication of the revised construction schedule, certified progress reports, payment records and the relevant provisions of the May settlement.

With December approaching, Guyanese households and businesses require a reliable account of what electricity will be available, when it will reach the grid, and what the final cost to the country is likely to be.

The May settlement established measurable commitments. The public now needs to know whether those commitments will be honoured, renegotiated or enforced.

ShareTweetSendShareSend

Related Posts

Editorial

Who Really Controls Guyana’s Future?

by Admin
October 25, 2026

Sovereignty is more than a flag, a national anthem or the right to occupy a seat at the United Nations....

Read moreDetails
Editorial

The State Must Answer for Kitty Shooting

by Admin
October 18, 2026

Our country has been asked to accept something it should refuse: that a police officer who admits firing on the...

Read moreDetails
Editorial

Gov’t Human Rights Claims at IPU Collide With Guyana’s Reality

by Admin
October 11, 2026

The People’s Progressive Party/Civic (PPP/C) government may present Guyana to the international community as a country committed to human rights,...

Read moreDetails
Next Post
Chinese Foreign Ministry spokesperson Guo Jiakun

China opposes US smearing, stigmatization of Confucius Institutes


EDITOR'S PICK

Mark will not make his ‘Mark’

December 6, 2022

Senior Finance Minister oversees signing of Agreements between GPL and GPSU, GUYOIL and CCWU

May 19, 2025
Prime Minister Mia Amor Mottley addresses Barbados 58 independence anniversary.

BARBADOS | From Debt Crisis to Renaissance, Barbados Charts Bold Course at 58

December 1, 2024
GHK Lall

Fighting For Freedom: Thinking, Press, Conscience 

June 27, 2026

© 2024 Village Voice

No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us

© 2024 Village Voice