Dear Editor,
What Guyanese are witnessing is a pattern of energy sector mismanagement under the stewardship of Bharrat Jagdeo, where grand promises are made, billions are committed, deadlines are missed, costs go up and households are left waiting for the benefits.
Let us not forget Skeldon was presented as a transformational investment that would modernise the sugar industry and provide DEPENDABLE electricity to Berbice. The project cost over US$187 million, way over its original cost, suffered serious operational and design deficiencies, and never truly delivered with respect to its cogeneration function.
Today, we are witnessing a similar pattern unfolding at Wales, except that the financial exposure is far greater. A project originally for completion in December 2024, with a 300 MW generating capacity and promises of a 50% reduction in electricity bills, faced another major financial request of GY$24.7 billion, or US$118.4 million from Parliament last Monday.
Jagdeo cannot continue to occupy the position of chief architect and defender of the country’s energy policy when things are going well, and then retreat into explanations about contractors, technical difficulties and external circumstances when things go wrong. He was President when the Skeldon project was commissioned, and he remains a central figure in the policy direction and political defence of the Wales project. He must answer for the decisions, the planning, the contractual arrangements and the financial consequences.
The public is entitled to know why the Government proceeded with Wales without adequately resolving the risks associated with site preparation and soil conditions, why the project has been delayed repeatedly, and what the final cost will be. It is not enough to tell Guyanese that negotiations have resolved contractual disagreements. Resolving a disagreement does not erase the financial consequences of the decisions that produced it.
The November 27th announcement by Jagdeo that the first 220 MW will not be available until March 2027, with full capacity expected around June 2027, is another admission that the Government’s promises have not materialised within the timeframes given to the country. We are now two and a half years beyond the original completion deadline. Meanwhile, the Government has sought just over GY$54.49 billion in budgetary provisions and requests associated with the project for 2026 alone.
Guyanese must think carefully what those numbers mean and not take them lightly. They represent public resources that could have been directed towards schools, hospitals, roads, drainage, public service wage increase and the many other pressing needs of working class Guyanese.
The position by the government that another parliamentary appropriation is an acceptable step towards progress, is rejected. Parliament has a responsibility to integrate the reasons for additional expenditure, to examine the performance of the project managers and contractors, and to establish whether the country is receiving value for money. Guyanese must demand a comprehensive accounting of the original contract, supplementary expenditure, additional site works, storage, insurance, brokerage, financing and all other costs arising from these delays.
The Government must also explain what contractual protections exist to prevent Guyanese taxpayers from being repeatedly exposed to escalating costs.
Most importantly, the people must not be forgotten in this discussion. The businesswoman in Linden who lost her meat, the manufacturer in Berbice who suffered 45 hours of blackouts, the shopkeeper in Georgetown who is forced to operate his business on generators, the pensioner and the ordinary household are still contending with the consequences of daily blackouts. They were promised relief. They were promised cheaper power. They were promised that the country’s newfound oil wealth would transform their circumstances. Instead, they are being asked to finance the consequences of decisions made by people who continue to assure them that everything is under control.
The question is not how many billions the Government is prepared to spend. The question is how many times Guyanese must pay for the same failures of planning, judgement and accountability.
Guyanese cannot afford another Skeldon. We cannot allow Wales to become a monument to political promises, escalating expenditure and unfulfilled expectations. Oil wealth must translate into reliable electricity, lower production costs, stronger businesses and a better standard of living. That is what Guyanese deserve, and that is what this Government must be held accountable for delivering.
Yours truly,
Hon Sharma Solomon
Member of Parliament