Friday, November 13, 2026
Village Voice News
ADVERTISEMENT
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us
No Result
View All Result
Village Voice News
No Result
View All Result
Home News

Patterson Criticises PPP/C Over Gas-to-Shore Project’s Cost Overruns and Site Selection Failures

"This is worse than the failure of the Skeldon Sugar Factory—and ten times more expensive"

Admin by Admin
October 21, 2025
in News
Alliance for Change  Chairman,  and interim Leader David Patterson MP

Alliance for Change Chairman, and interim Leader David Patterson MP

0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

Interim Leader of the Alliance For Change (AFC) and spokesperson on Oil and Gas, David Patterson, has criticised the People’s Progressive Party/Civic (PPP/C) Government for ignoring feasibility studies conducted under the 2015–2020 A Partnership for National Unity and Alliance for Change (APNU+AFC) administration regarding the Gas-to-Shore Energy Project.

Patterson, who served as Minister of Public Infrastructure under the APNU+AFC Government, had oversight of the project during its initial planning phase.

READ ALSO

GNBS seizes & destroys over 20,000 pieces of substandard and unsafe electrical items and cigarettes

Speaker’s Reversal Blocks Parliamentary Scrutiny, Leaves Ministers Facing No Questions

The flagship Gas-to-Shore Project at Wales, intended to bring natural gas from offshore to power a 300 MW facility, has become a focal point of national scrutiny. Initially announced in 2021 with an estimated cost of US$900 million and a promise to cut electricity prices to under 5 US cents per kWh, the project’s price tag has now reportedly ballooned to over US$2.2–2.4 billion.

While the government has already spent US$400 million from local funds and awaits financing from the U.S. Exim Bank, delays and contractor disputes have pushed back the completion timeline, possibly into 2026.

Though offshore pipeline works are progressing, onshore construction remains incomplete. Independent analysts and the political opposition have raised growing concerns over feasibility, accountability, and a lack of transparency throughout the project’s development.

“In 2020, the PPP/C Government promised to conduct studies for the Gas-to-Shore Project, but they never did,” Patterson said.

His comments come in the wake of revelations that the Government of Guyana has spent an additional US$100 million over the project’s original budget, leading to significant delays in its completion.

Speaking to Village Voice News, Patterson said the selected site at Wales was unsuitable for the type of infrastructure required. He noted that the APNU+AFC Government had commissioned five separate feasibility studies during its term in office.

“We left five studies there, and none of them recommended the Wales site,” Patterson stated. “The preliminary studies pointed to Clonbrook in the Mahaica Region Five area. ExxonMobil and everyone else agreed that it was the best location for the Gas-to-Shore Project.”

Further concerns were raised during the Guyana International Business Conference (IBC), held in Georgetown from October 15 to 17, 2024, where Lindsayca Chairman Nelson Drake revealed that liquid was discovered at the project site and warned of potential hazards stemming from poor site selection.

“The equipment we’re putting on the site is essentially a gas processing facility, which can easily become a bomb if not properly managed,” Drake said. “The Simmons turbine and the power island must be perfectly aligned.”

Originally, the PPP/C Government had pegged the cost of the Gas-to-Shore Project between US$300 million and US$800 million. According to Patterson, the cost has now ballooned to over US$2.5 billion—and the project remains incomplete.

Patterson also criticised Vice President Bharrat Jagdeo’s earlier claim that building the facility at Wales was a “no-brainer.” In a 2021 interview, Jagdeo described the project as a “no-brainer,” emphasising its potential to reduce electricity costs drastically—from approximately 30 US cents per kWh to as low as 4 US cents per kWh by switching from diesel to natural gas.

However, Patterson forecast differently stating that “I can say without contradiction that the promised delivery cost of 3 US cents per kilowatt-hour is now increasing.” According to him, “Guyanese will feel the burden of that cost. The [Wales Project] is worse than the failure of the Skeldon Sugar Factory—and ten times more expensive.”

ShareTweetSendShareSend

Related Posts

News

GNBS seizes & destroys over 20,000 pieces of substandard and unsafe electrical items and cigarettes

by Admin
November 13, 2026

The Guyana National Bureau of Standards (GNBS) plays a key role in ensuring that specified products sold, manufactured, imported and...

Read moreDetails
Speaker Manzoor Nadir presiding over the 2026 Budget Debates
News

Speaker’s Reversal Blocks Parliamentary Scrutiny, Leaves Ministers Facing No Questions

by Admin
November 13, 2026

By Mark DaCosta- Disallowing a question does not answer it, and in our National Assembly that distinction now matters more...

Read moreDetails
One-year-old Traiden Tanner
News

One-Year-Old Dies At Sophia Daycare As Child Protection Agency Launches Investigation

by Admin
November 13, 2026

The Ministry of Human Services and Social Security has launched an immediate investigation into the death of one-year-old Trayden Tanner...

Read moreDetails
Next Post
L-R Foreign Affairs Minister Hugh Todd and WIN Presidential Candidate Azruddin Mohamed

Gov’t Lied, Falsely Linked Citizens to Foreign Adversary


EDITOR'S PICK

We need the truth on the Wismar massacre

May 25, 2023

While grass is growing the horse is starving; Guyanese must stand up and claim their fair share

June 30, 2024
Frank Lampard has been out of a job since being sacked as Chelsea manager a year ago

Frank Lampard offered Everton managerial job to replace Rafael Benitez

January 30, 2022

𝐅𝐨𝐫𝐦𝐞𝐫 𝐌𝐚𝐲𝐨𝐫 𝐏𝐭.𝐔𝐛𝐫𝐚𝐣 𝐍𝐚𝐫𝐢𝐧𝐞 𝐜𝐞𝐥𝐞𝐛𝐫𝐚𝐭𝐞𝐬 𝐃𝐢𝐰𝐚𝐥𝐢 𝐚𝐭 𝐭𝐡𝐞 𝐒𝐜𝐡𝐨𝐨𝐥 𝐨𝐟 𝐭𝐡𝐞 𝐍𝐚𝐭𝐢𝐨𝐧𝐬, 𝐇𝐨𝐧𝐨𝐮𝐫𝐢𝐧𝐠 𝐂𝐮𝐥𝐭𝐮𝐫𝐚𝐥 𝐃𝐢𝐯𝐞𝐫𝐬𝐢𝐭𝐲 𝐚𝐧𝐝 𝐄𝐱𝐩𝐫𝐞𝐬𝐬𝐢𝐨𝐧

November 12, 2023

© 2024 Village Voice

No Result
View All Result
  • Home
  • News
  • Sports
  • Editorial
  • Letters
  • Global
  • Columns
    • Eye On Guyana
    • Hindsight
    • Lincoln Lewis Speaks
    • Future Notes
    • Blackout
    • From The Desk of Roysdale Forde SC
    • Diplomatic Speak
    • Mark’s Take
    • In the village
    • Mind Your Business
    • Bad & Bold
    • The Voice of Labour
    • The Herbal Section
    • Politics 101 with Dr. David Hinds
    • Talking Dollars & Making Sense
    • Book Review 
  • Education & Technology
  • E-Paper
  • Contact Us

© 2024 Village Voice